Spears Creek Church Rd Widening

Districts 9, 10

The project will consist of potential improvements along the existing roadway from North of the intersection with Two Notch Road (US 1) and just before the westbound I-20 entrance/exit ramps, for a total length of approximately 2.3 miles. From Two Notch Rd to Earth Rd is 3‐lane, from Earth Rd to I‐20 is 5‐lane.

 

Project Status:

  • Final construction plans have been submitted to DOT on February 18, 2026 for review. Utility coordination is still ongoing, which includes preparation of utility agreements, final reports, no-cost letters, utility relocation plans, and utility special provisions. There are 45 parcels for ROW: 36 offers made, 14 fee deeds secured, and 23 permissions secured.