Sunset Drive Sidewalk
District 4
Project consists of a 5 ft. wide sidewalk along the north side of Sunset Drive from River Drive to Elmhurst Road.

Project Status:
- This project is 99% complete. A ribbon cutting ceremony was held on November 12, 2025. To closeout the project, there is some road leveling that needs to take place, some asphalt paving needs to be placed. The project is anticipated to be 100% complete by April 2026.
Planned Route: