Percival Road Sidewalk
Districts 6,8,10
Project consists of a 5 ft. wide concrete sidewalk on one side along Percival Road from Forest Drive to Decker Boulevard.

Project Status:
- The project has been awarded. The contractor has finished pouring sidewalks, the mucking operation is complete, and all of the guardrail has been installed. The last item on the to-do list is pouring the asphalt pavement near Decker Blvd.
Planned Route: