Broad River Road Widening
District 1
Project Status:
- Salem Church Road realignment is in place and is operational. Additional improvements continue at this location. MCEC has installed around 10 cast iron poles out of 51 total. Foundations for 6 engineered poles have been inspected and approved allowing for large, engineered poles to be scheduled. Once MCEC relocations are in place between Royal Tower Road and N Woodrow Street, water and sewer relocation can be fully underway.