Broad River Corridor NIP

Districts 2,4,5

The scope of the proposed neighborhood improvement project(s) will be determined in Phase 1 (concept phase) of this project. Project(s) and scope options will be selected directly from the approved Richland County Neighborhood Master Plan and refined based upon public and stakeholder input and available funding.

 

Project Status:

  • The Broad River Corridor Concept Report was completed in April 2019 and approved by County Council in May 2019. Preliminary right-of-way plans were submitted to SCDOT in April 2024, with an Authorization to Proceed (ATP) for right-of-way activities issued in September 2024. The project is under SCDOT review, pending agency comments and formal construction plan approval. Right-of-way acquisition continues, with several parcels in condemnation. Upon SCDOT approval and finalization of all right-of-way acquisitions, the project will be cleared up for construction.