Broad River Road Widening

District 1

The proposed scope recommends a 5-lane section (4 travel lanes and a center turn lane) between Royal Tower Drive and Dutch Fork Road. Bicycle and pedestrian accommodations shall include sidewalks from Royal Tower to Woodrow (SR S-40-27).

 

 

Project Status:

  • Salem Church Road realignment is in place and is operational. Additional improvements continue at this location. MCEC has installed around 10 cast iron poles out of 51 total. Foundations for 6 engineered poles have been inspected and approved allowing for large, engineered poles to be scheduled. Once MCEC relocations are in place between Royal Tower Road and N Woodrow Street, water and sewer relocation can be fully underway.

Planned Route: