Decker/Woodfield NIP Hunt Club Rd
Districts 3,8,10
The scope of the proposed neighborhood improvement project was determined in Phase 1 (concept phase) of this project. The project scope was selected directly from the approved Richland County Neighborhood Master Plan and refined based on public and stakeholder input and available funding. The Hunt Club Road project begins at O'Neal Court and runs to Chatsworth Road. The project is .5 miles long and consists of a 5 ft. wide sidewalk along the length of the project.

Project Status:
- A pre-construction meeting for the project was held on March 11, 2026. Currently, Subsurface Utility Engineering activities are completed. The findings identified approximately 1,100 linear feet of conflict between the proposed drainage structures and the existing waterline. The SUE team is currently scheduling test holes to verify the existing waterline elevations. Based on the results, the drainage layout may be modified to avoid vertical conflicts by shifting the side drainage system closer to the existing right-of-way. This approach may include installing junction boxes and short perpendicular pipe connections to the catch basins, which would help reduce structure depths and minimize utility impacts. The estimated completion date for the final construction plans is June 12, 2026.
Planned Route: