Dirt Road Paving Package “P”

Districts 7,10

Dirt Road Paving Package "P" covers the paving of five dirt roads.

  • Larger St. - District #07 (1,853 LF)
  • Spring Creek Rd. - District #10 (3,226 LF)
  • Smithcreek Rd. - District #10 (1,256 LF)
  • Goodwin Way - District #10 (1,531 LF)
  • Adams Scott Rd. - District #10 (3,484 LF)

 

Project Status:
  • Construction commenced in October 2025. The Contractor is working with all utility companies for utility relocation. The construction is 43% completed. Adam Scott Road is paved.
Planned Route: