Jackson Creek Greenway
District 3
This proposed project will consist of a greenway that extends from North Trenholm Road Extension and meandering along a route to be determined generally following Jackson Creek and terminating at Trenholm Road near Decker Boulevard. Total length of the greenway is proposed to be 1.3 miles.

Project Status:
- The Jackson Creek Greenway alignment has been revised due to unsuccessful ROW negotiations with key property owners. The project team was unable to secure access across the Palmer properties, requiring a shift in approach. A new preliminary alignment of approximately one mile has been developed based on field verification and avoidance of constrained parcels. This revised corridor reflects site conditions observed during the recent field walk. The project is now advancing into concept design using this updated alignment. Bridge feasibility and overall constructability will be evaluated as part of the next phase.
Planned Route: