The widening of Atlas Road from 2 lanes to 5 lanes between Shop Road and Garners Ferry Road. Phase 1A covers all utility relocation work.
PROJECT STATUS: Notice to Proceed issued for November 11, 2024. Utility installation underway.
Phase 1B – Roadway
The widening of Atlas Road from 2 lanes to 5 lanes between Shop Road and Garners Ferry Road. Project will include 2 bike lanes, curb and gutter and two sidewalks.
PROJECT STATUS: Construction start will be confirmed based on Phase 1A progress.
Phase 2
The widening of Atlas Road from 2 lanes to 3 lanes between Bluff Road and Shop Road. Improvements will include 2 bike lanes, curb and gutter and 2 sidewalks.
PROJECT STATUS: Plans are being updated per SCDOT comments.