SERN 2 Rabbit Run Sidewalk
District 11
The Southeast Richland Neighborhood Master Plan includes three projects that are included in the Transportation Penny Program. The three projects are: (1 Multi‐use path on Rabbit Run from Garners Park Road to Lower Richland Blvd; (2 Multi‐use path on Lower Richland Blvd from Rabbit Run to the High School; (3 Garners Park Road: 2‐lane road on new location from US 76/378 (Garners Ferry Road/Garners Ferry Sports Complex to S‐2089 (Rabbit Run, approximately 0.5 miles.

Project Status:
- SCDOT approved comment responses awaiting written authority (NTP). Encroachment permit is approved. OET is 98% complete with design. OSBO is awaiting OET cost estimate for setting SLBE goal. Procurement should receive project for pre-bid in the near future.
Planned Route: