Shop Road Widening
District 10
The project consists of widening the existing roadway to five lanes (two lanes in each direction with a 13-foot center median) with 5’ bike lanes, curb and gutter, and sidewalks on both sides of the road from the intersection with George Rogers Blvd. toward Mauney Drive for an approximate distance of 2.2 miles. No improvements will be done to the roadway at the intersection with George Rogers Blvd.

Project Status:
- ROW acquisition continues where plans are sufficiently defined, while additional tracts remain on hold pending design revisions. Environmental review remains 90% complete, with utility coordination at 65% and utility design at 35%. Norfolk Southern completed its 60% plan review, with comments being incorporated into subsequent plans. Drainage and design coordination continue, and the consultant is compiling project revisions and an updated schedule for County review.