Shop Road Widening
District 10
The project consists of widening the existing roadway to five lanes (two lanes in each direction with a 13-foot center median) with 5’ bike lanes, curb and gutter, and sidewalks on both sides of the road from the intersection with George Rogers Blvd. toward Mauney Drive for an approximate distance of 2.2 miles. No improvements will be done to the roadway at the intersection with George Rogers Blvd.

Project Status:
- Updated ROW plans and submitted to SCDOT on 10/2/2025. Will begin ROW acquisition once approval from SCDOT. Phase II Environmental Site Assessment has been complete. Utility Relocation plans have been received from the utility providers. All ROW title work is complete. Waiting on signed ROW plans before beginning to acquire new ROW and permissions. Sent updated plans to Norfolk Southern in May 2025 and waiting their review to determine if a new Preliminary Engineering agreement is needed.