Clemson Road and Sparkleberry Lane Intersection

Districts 9, 10

The proposed scope recommends improvements to the Clemson Road and Sparkleberry Lane intersection to increase intersection capacity. The project limits along Clemson Road begin at the Corporate Park Drive/Frontage Road Intersection and end at Sparkleberry Crossing Road intersection and the limits along Sparkleberry Lane begin at Clemson Road and end at Mallet Hill Drive.

 

Project Status:

  • ATP for ROW issued by SCDOT on 8/12/2025. Final roadway, hydro, bridge, and geotechnical design are ongoing. Stormwater appurtenances are being reviewed against potential utility conflicts to minimize and/or avoid conflicts. R/W plans are being reviewed by the utility coordination team to identify conflicts. Permissions, initial contact, and title work have been requested for all involved parcels.

Planned Route: